LIST OF ALL GENERATING UNITS WHOSE POWER IS SCHEDULED TO HPSEBL SYSTEM


  HPSEB OWNED (Own) 
STATION. CAPACITY
(MW).
LOCATION. RUN BY.
  LARJI   126   LARJI   HYDRO POWER 
  BHABHA   120   BHABHA   HYDRO POWER 
  BASSI   60   BASSI   HYDRO POWER 
  GIRI   60   GIRI   HYDRO POWER 
  GHANVI   22.5   GHANVI   HYDRO POWER 
  ANDHRA   16.95   ANDHRA   HYDRO POWER 
  BANER   12   BANER   HYDRO POWER 
  KHAULI   12   KHAULI   HYDRO POWER 
  GAJ   10.5   GAJ   HYDRO POWER 
  BINWA     BINWA   HYDRO POWER 
  THIROT   4.5   THIROT   HYDRO POWER 
  PTKR   16   PATIKARI   HYDRO POWER 
  MICROS   44.85   MICROS   HYDRO POWER 



















  NTPC OWNED (Central Sector) 
STATION. CAPACITY
(MW).
LOCATION. RUN BY.
  SINGR   2000   SIGRAULI   THERMAL POWER 
  RHND-I   1000   RIHAND   THERMAL POWER 
  KHLGN-I   840   KHEL GAON   THERMAL POWER 
  RHND-II   1000   RIHAND   THERMAL POWER 
  DDRIT   840      THERMAL POWER 
  UNCH-I   420   UNCHAHAR   THERMAL POWER 
  UNCH-II   420   UNCHAHAR   THERMAL POWER 
  UNCH-III   210   UNCHAHAR   THERMAL POWER 
  DDRGF   830   DADRI   THERMAL POWER 
  DDRRF      DADRI   THERMAL POWER 
  DDRLF      DADRI   THERMAL POWER 
  FARAKKA    2100   NABARUN-WEST BENGALl    THERMAL POWER 
  KOLDAM   800   BARMANA   HYDRO POWER 
  SINGRAULI_SOLAR      SIGRAULI   SOLAR 
  RHND3   950   RIHAND   THERMAL POWER 
  KOTESHWAR   200   KOTESHWAR    
  JHAJJAR   950   JHAJJAR    
  DDRIT-II   980       
  ADHPL      AD HYDRO    
  KHLGN-II      KHEL GAON   THERMAL POWER 
  ANTGF   419   ANTA   THERMAL POWER 
  ANTRF      ANTA   THERMAL POWER 
  ANTLF      ANTA   THERMAL POWER 
  AURGF   663   AURIYA   THERMAL POWER 
  AURRF      AURIYA   THERMAL POWER 
  AURLF      AURIYA   THERMAL POWER 
  IPP OWNED (Independent) 
STATION. CAPACITY
(MW).
LOCATION. RUN BY.
  BASPA-II   300   BASPA   HYDRO POWER 
  MALANA   86   MALANA   HYDRO POWER 
  NPC OWNED (Central Sector) 
STATION. CAPACITY
(MW).
LOCATION. RUN BY.
  NAPP   440      ATOMIC POWER 
  RAPP-III         ATOMIC POWER 
  RAPB   440      ATOMIC POWER 
  RAPS         ATOMIC POWER 
  RAPP-IV         ATOMIC POWER 
  BBMB OWNED (Central Sector) 
STATION. CAPACITY
(MW).
LOCATION. RUN BY.
  BHKRA   1000   BHAKRA   HYDRO POWER 
  DEHAR      DEHAR   HYDRO POWER 
  PONG      PONG   HYDRO POWER 
  NTPC (E) OWNED (Central Sector) 
STATION. CAPACITY
(MW).
LOCATION. RUN BY.
  FRKKA   1600   FRKKA   THERMAL POWER 
  PSEB OWNED (Shared) 
STATION. CAPACITY
(MW).
LOCATION. RUN BY.
  SHANAN      SHANAN   HYDRO POWER 
  RSD      RANJIT SAGAR DAM   HYDRO POWER 
  THDC OWNED (Central Sector) 
STATION. CAPACITY
(MW).
LOCATION. RUN BY.
  TEHRI   1000   TEHRI   HYDRO POWER 
  NJHPS OWNED (Central Sector) 
STATION. CAPACITY
(MW).
LOCATION. RUN BY.
  NJPC   1500   NATHPA   HYDRO POWER 
  UKND OWNED (Shared) 
STATION. CAPACITY
(MW).
LOCATION. RUN BY.
  YAMUNA         HYDRO POWER 
  UP OWNED (Shared) 
STATION. CAPACITY
(MW).
LOCATION. RUN BY.
  KHARA   72      HYDRO POWER 
  ADANI OWNED (Shared) 
STATION. CAPACITY
(MW).
LOCATION. RUN BY.
  MUNDRA_UMPP    4620   GUJARAT   THERMAL POWER 
  EPPL OWNED (Shared) 
STATION. CAPACITY
(MW).
LOCATION. RUN BY.
  MALANA2    100   MALANA-KULLU   HYDRO POWER 
  MNRE OWNED  
STATION. CAPACITY
(MW).
LOCATION. RUN BY.
  SECI_SOLAR      RAJSTHAN   SOLAR 
   * Maximum Demand of the State on Dated 12th December 2017 at 18:30 Hrs : 1368MW   * SINGLE LINE NETWORK DIAGRAM OF HPSEBL (66KV and above)   * Notice for 142nd OCC meeting.   * Deviation Settlement Account for the week 201117-261117   * Provisional REA for the month of November, 2017   * Allocation of Power from CGSs (Revision # 11/ 2017-18 w.e.f. 00:00 hrs of 1.12.2017)   * Minutes of 141st OCC meeting.   * Notice for 12th TeST Sub-Committee Meeting.   * Agenda for 141st OCC meeting.   * Final REA for the month of April, 2017   * Agenda for 37th TCC and 40th NRPC Meeting.   * Minutes for the 36TCC Meeting.   * Notice for the 37th TCC and 40th NRPC Meeting.   * Allocation of Power from CGSs (Revision # 06/ 2017-18 )   * Minutes for 11th meeting of TEST Subcommiittee.   * Agenda for 11th meeting of TEST Subcommiittee..   * Notice Inviting Tender for Sale of Renewable Power (Non-Solar) on Short Term Basis.   * Atlas of HPSEBL Power Grid with details of Sub-Stations (66kV & above), Optical Network and PLCC network of HPSEBL. * MULTI-YEAR TARIFF PETITION FOR 3rd CONTROL PERIOD FY 2014-15 TO FY 2018-19 * HPSEBL - TARGET MONITORING & REVIEW SYSTEM      * GoHP Notification dated 10-06-2010: Notification & Agreement       * Procedure for Real Time Operations.    * What to do for WannaCry attacks: Please ensure all of your Windows environments have been updated as described in Microsoft Security Bulletin MS17-010 - Critical. Microsoft is providing Customer Guidance for WannaCrypt attacks    * Prevention of WannaCry Ransomware Threat - WebCast Session by Indian Computer Emergency Response Team (CERT-In)
OUR  MOTTO    RELIABILITY,  SECURITY  &  ECONOMY  IN  POWER  SYSTEM  OPERATION
Copyright 2004-13 www.hpaldc.org, All Rights Reserved, Site Maintained by HPALDC - HPSEBL
Best viewed in Crome with 1440 by 900 Screen Resolution
Your IP is: 192.168.9.1